translate

8.3.2.1: Change in level

Where there is a change in floor level that is integral to the ICT then it shall be ramped with a slope no steeper than 1:48.

Exceptions:

a) If the change in floor level is less than or equal to 6,4 mm (¼ inch) the change may be vertical as shown in Figure 1.

A diagram illustrating the content of the text 8.3.2.1 a)
Figure 1: Vertical change in level

b) If the change in floor level is less than or equal to 13 mm (½ inch) the change may have a slope not steeper than 1:2 as shown in Figure 2.

A diagram illustrating the content of the text 8.3.2.1 b)
Figure 2: Bevelled change in level

Testing methods

a)

Type of compliance Inspection and measurement (a)
Pre-conditions
  1. There is a change in level integral to the ICT.
Procedure
  1. Check that the change in level is ramped with a slope less than1:48.
Result  Pass: Check 1 is true
 Fail: Check 1 is false

 

b)

Type of compliance Inspection and measurement (b)
Pre-conditions
  1. There is a change in level integral to the ICT.
  2. The change in level is less than or equal to 6,4 mm.
Procedure
  1. Check that the step is vertical or ramped.
Result  Pass: Check 1 is true
 Fail: Check 1 is false

 

c)

Type of compliance Inspection and measurement (c)
Pre-conditions
  1. There is a change in level integral to the ICT.
  2. The change in level is less than or equal to 13 mm.
Procedure
  1. Check that the ramp has a slope less than 1:2.
Result  Pass: Check 1 is true
 Fail: Check 1 is false

There is currently no content classified with this term.